This is a lightweight getting started guide for our team while formalized training material is being developed.

How to Start Creating Your OTL

Object List and Task Outline

Start with a list of your objects. When you believe you've captured all your deliverables, start an outline to elaborate your tasks. Include the whole SDLC for development tasks. Formal testing planning would be a set of its own objects. Concurrently or after, build your milestone list. Below is an example of the objects (deliverables) and a task outline for the migration project itself. I started with the object list and its types and through collaboration with the team we talked through the tasks. This provided a good starting point for the detailed tasks in the OTL template itself where things became more clear, estimated, adjusted, and scheduled. We included the red PMO touchpoints here because I used this later in the task descriptions to call out the parties involved.

...

ObjectObject TypeTasks
FIS Migration PlanProject Plan
  • Identify Projects / Products and their Leads
  • Create Project / Product Spaces in JIRA 
  • Build out Confluence
    • Create vision statement
    • Identify Team Members
    • Scope Statement
    • Create OTL templates
Methodology Training SessionTraining Session
  • Introduce SCRUM, focus on time boxing work
Ontology Training SessionTraining Session
  • Ontology workshop, IPPS leads (by 4/21)
JIRA OTL Training SessionTraining Session
  • JIRA OTL training, FIS team and IPPS team (by 4/21)
Professional SCRUM TrainingTraining Session
  • Interview trainers
  • Design session (3rd for Ontology)
  • Budget request
  • Identify team and projects
  • Schedule training
  • Execute training (end of May)
Project OTLs+Project Plan
  • Object List
  • Develop OTL
  • Review OTL
  • Load OTL
RetrospectiveCloseout Document
  • Meet with task force for feedback and actions
Project OTLs+Project Plan
  • Object List
  • Develop OTL
  • Review OTL
  • Load OTL
RetrospectiveCloseout Document
  • Meet with task force for feedback and actions

Milestones

Milestones come out of your communication plan. What do you need to tell your stakeholders? You might want to have things like kickoff, final delivery, but during planning you might have a major go / no go decision point. Maybe you want to communicate when certain modules are ready. Below is an example of the milestones for the migration project itself.

MilestoneDate
Projects & Leads Identified and Methodology Selected3/17/2017
Estimated Project Schedule4/9/2017
Leads Start OTL Development4/110/2017
FIS Schedule Finalized4/25/2017
FIS Engine Started6/2/2017 (ballpark estimated)

 

The Full OTL Template

The following is an example of the 3 types of rows you will find useful in generating your OTL.

...