Due end of day Tuesday, August 6, 2024

UAT Action needed by Report Developers and Data Integration Developers
Status
colourGreen
titlecomplete

...

  • All DEV0 enhancements will be migrated to Hana Production. Due to the volume of moving data, the migration will happen in to stages.

    • Monday, August 19: Normal data loads.

      • SAH will be available with data as of August 18, 11:59pm.

    • Tuesday, August 20: SAH data loads will be halted, therefore SAH data will be stale.

    • Wednesday, August 21: SAH views will be migrated. SAH Production will NOT be available during this time.

      • Hana QA will be available with ISIS Production data.

      • Cognos report developers can run reports in Cognos DEV using Hana QA to see ISIS Production data.

      • Tableau developers can point their reports at the SAH -QA data sources to see ISIS Production data.

      • Report developers will recieve error messages or incomplete data if they attempt to run their report against SAH Production.

      • Banners will be placed on https://bah.ucsd.edu/student/index.html and https://status.ucsd.edu/

    • Thursday, August 22: SAH Non-LMS views are back up and refreshed per our standard 11:59pm of the night before.

      • This includes all SAH Core views, Restricted Views and Admission views.

      • Data loads for non-LMS views will restart per our standard schedule.

      • SAH LMS views will continue to be unavailable.

    • Friday, August 23 - Sunday, August 25: SAH LMS views are not available.

      • SAH Non-LMS views will be available and refreshed per our standard daily schedule.

    • Monday, August 26: SAH LMS views are back up.

      • Data in all SAH views will be refreshed per our standard 11:59pm of the night before.

SAH DEV0 Phase 2 – Starting Oct 14, 2024

Views in focus:

...