Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

4

Project

Discussion Items

AIs

1

/wiki/spaces/SAHFSPT/pages/1734901810

2

/wiki/spaces/RAH/pages/1810006128

32

SAH projects for next fiscal year

Priorities other than TSS:

  1. FSPT - Chancellor deciding on priority Jan 2025

  2. Slate Grad in SAH - check with Mary

    1. what do they want exactly?

  3. UAchieve in SAH - check w/Cindy

  • sync to chat about Uachieve requirements
3

Financial AR data in FINAH

  • roughly about 10 tables

  • Lref gdrive file
    urlhttps://docs.google.com/spreadsheets/d/1dswuhAHygqRUFrRd7k2AeeY_gowe1hl9x2XeuAHouB8/edit?gid=0#gid=0

  • data’s dirty

  • many to many relationships that don’t map out cleanly

  • it’s a receivables module

  • Ying and Moh can access

  • PPM contract has receivables data in it already

  • send out invoices and we get paid

  • 1 receipt can pay 1 part of invoice

  • 1 receipt can pay multiple invoices

  • issue credit memos that reverse invoices and invoice doesn’t get paid

  • grain will be really important and how we’ll divide up the views

  • Maruthi and Heather are doing these KPIs manually right now

    • let me know what your # of hours

  • Health Sciences also wants this data in the hub

  • data fields will have overlap with contract and contract revenue views

  •  Alamuri, Maruthi will pull together roughly how many Financial AR fields are needed to be added to FinAH
  •  Alamuri, Maruthi will let Mindy know total number of hours spent on manually doing KPIs

4

Ecotime in EAH

5

HireOnline in EAH

6

Deprecation of legacy systems

add to MTC SOW

7

8

TSS

  • Invenio SOW?

    • Shayan and Kevin discussing IP

    • can we start in good faith in meantime?

    • still need detailed OTL

89

IR contract (MTC)

  • fixed price bid

    • UCSD needs to provide back to MTC

910

Phase 3

  • Can any tasks be started now?

    • check with Kenny if any of the BVs impacts the Nov app views that Sama’s working on

1011

Validation phase 2

  • BIA is validating CVs as they become available in DEV

    • helps with catching issues early so won’t be replicated elsewhere

    • less validation needed when we enter official QA phase

1112

Outstanding OTLs for Erin

  • Maximo in FACAH

  • Jira in RAH

  • possible joint budget ask from RMP and OCGA

  • next fiscal yr - July 2025- July 2026

  • Michael Weinfeld submitted a ticket for AP data (Academic Personnel)

    • not part of ESR

    • would need to be prioritized after TSS go live

  • what happens if TSS go live slips? What are the backlogged projects' dependent on ?

    • need data steward to prioritize for each hub

  • 3 yr need vs 1 yr

  • contract employee (not PO)

    • would be a view developer / architect

    • Bhavya’s moving into BI role

  •  Mindy check on data sizing and OTLs for Maximo, Jira (Ernesto/Nicole), Slate Grad (Jonathan?), uAchieve (Jonathan), Financial AR data (Heather), AP Online (Andreas), FSPT

...