2024-11-28 AH Project Portfolio Review
Participants
Judy
Mindy
Goals
Resource allocations
Roadmap
Backlog items
Risks/escalations
Time Tracking: AHM-789
Discussion topics
Roadmap
https://tableau.ucsd.edu/#/views/MindyMilestones/ProjectMilestoneGantt?:iid=2
Resource allocations and utilization
Projects
AH plan: https://its-pro.ucsd.edu/secure/PortfolioReportView.jspa?r=AGfFr
Summary view: Login - Advanced Roadmaps - ITS PRO
Project | Discussion Items | AIs | |
---|---|---|---|
1 | hours broken down by resource type, so that we can then estimate costs |
Mindy look at % breakdown of facilities project
|
|
2 | https://ucsdcollab.atlassian.net/wiki/spaces/RAH/pages/1810006128 | ~1000 hrs
|
|
3 | SAH projects for next fiscal year | Priorities other than TSS:
| @Jonathan Whitman will FU with Carlo on Slate Grad requirements Dec 9, 2024 @Jonathan Whitman will FU with Anna on joining 12/9 SAH sync to chat about Uachieve requirements |
4 | Financial AR data in FINAH |
| @Alamuri, Maruthi will pull together roughly how many Financial AR fields are needed to be added to FinAH Dec 2, 2024 @Alamuri, Maruthi will let Mindy know total number of hours spent on manually doing KPIs Dec 2, 2024
|
5 | HireOnline in EAH |
|
|
6 | Deprecation of legacy systems |
|
|
7 | payroll account table change |
Mindy add to EAH agenda to discuss with Andy Mindy add to HANA sync to discuss w/ Nathalie |
|
8 | Ecotime in EAH | maybe |
|
9 | Maximo | maybe (~900 hrs) |
|
10 | TSS |
|
|
11 | IR contract (MTC) |
|
|
12 | Phase 3 |
|
|
13 | Validation phase 2 |
|
|
14 | Outstanding OTLs for Erin |
| Mindy check on data sizing and OTLs for Maximo, Jira (Ernesto/Nicole), Slate Grad (Jonathan?), uAchieve (Jonathan), Financial AR data (Heather), AP Online (Andreas), FSPT
|
Current AH project portfolio
key | summary | type | priority | status | Project go live date | Project Health | Executive Project Update | OTL Status |
---|