titleRisk Attributes and Definitions

Risk Evaluation Definitions

:

Mitigation Strategy Definitions:

  • Probability: Likelihood of the risk to occur

    • 1 = Unlikely

    • 2 = Likely

    • 3 = Almost Certain

  • Impact: Consequences for the project if the risk occurs

    • 1 = Minor

    • 2 = Major

    • 3 = Critical

Risk Score: Calculated by Probability * Impact (1-9 scale, 9 most severe)

The Mitigation Strategy for a risk should address the risk in one of four ways:

  • Avoid - pursuit of a completely different approach to the task, thus eliminating the risk

  • Transfer - moving the risk elsewhere (supplier or other organization)

  • Mitigate - developing a plan to reduce the consequence and/or the likelihood of a risk event occurring

  • Accept - allowing the risk to remain and dealing with the consequences if it happens

...

Expand
titleEvaluating an Issue

Issue Evaluation Definitions

:

  • Probability: Likelihood to occur or reoccur:

    • 1 = Unlikely

    • 2 = Likely

    • 3 = Almost Certain

  • Impact: Consequences for the project:

    • 1 = Minor

    • 2 = Major

    • 3 = Critical

Score: Calculated by Probability * Impact (1-9 scale, 9 most severe)

...