assuming no additional SAH field additions beyond what we know now and assuming no new integrations, it will take until july 2026 to complete the dev0 phase 2 and dev0 phase 3 work
can we find another pseudo-Kenny resource so can run 2 phases in parallel?
2
IRR and Registrar
3rd week meetings - who’s owner?
3
no; one phase builds on the other and too many moving parts
Sama - 60% on SAHR work and 40% on AI work
Bhavya will take over Sama’s CSC work
Kenny will need to do TSS remapping work as well so that will take time away from Dev0
add’l integrations and new data sources will be needed
Would Eric be interested in doing this?
base views are simpler so let’s delegate to someone non-Kenny
what can we run in parallel?
Chunk out the first set of BVs so it’s a round robin
Art can do BVs
Sama and Kenny can do IVs and CVs
Art could be writing the SQL code in the meantime
right now, Art is working on everything legacy-dw
aiming to finish dev0 phase 3 by March 2025
finish dev0 phase 2 by Jan 2025
TSS
provide them with initial mapping but we’ll have to hand-hold them through implementation (similar to UW and ASU)
ISIS and TSS running in parallel?
not sure; Erin will follow-up
Mindy Peng schedule 2 hr working session with Kenny, Judy, and Erin to hammer out structure plan for dev0 phases