Table of Contents | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Issues
Info |
---|
Issue is an item that is currently happening or has happened and is impacting the project. Issues are evaluated based on their impact to the project: 1 = Minor, 2 = Major, 3 = Critical All active issues must have a due date and action plan. For the action plan, you would use the Smart Checklist to document who is doing what to resolve the issue and when the action is due (for example, for an issue called "Many TSS risks are missing mitigation plans", I might have a Smart Checklist item called "Work with team to add mitigation plan to each risk - Brian Smith - 2/12/2025". Issue due dates should reflect when the action plan will actually be complete as best we can estimate, so they should never be dated in the past/overdue in Jira. |
...
title | Creating an "Issue" record in JIRA |
---|
...
Creating an “Issue” Record in JIRA
...
Screenshots
Risks
Info |
---|
Risks are items that might happen and will impact the project if it does occur. Risks are evaluated by three areas: Probability, Impact, and Risk Score. |
PLAN STRATEGY |
---|
The project team will identify an individual responsible for determining risk mitigation plan, or contingency plan, for each risk identified. This individual is also responsible for logging the risk in Jira. Risks with an overall risk score of 6, or higher, needs to follow the escalation process with governance. If a risk is not handled on time, it becomes an issue. The project team will conduct a working risk assessment session to identify initial risks. Larger projects may need multiple sessions to complete assessment. ITS PRO. Requirement: All active risks must have a Mitigation Plan and due date Due Date. If the assignee hasn't provided a Mitigation Plan yet, the plan can state something like "Mitigation Plan to be developed by @assignee by X/X" with X/X being a due date where the Assignee needs to complete the Mitigation Plan by. Due date should be when the risk is no longer a risk - for some risks (like "resources could get burned out") the risk will run the length of the project, and in those cases the estimated project close date (like 6/30/2026 for TSS) would be Due Date you'd putthat would be entered. Note:
|
Expand | ||||
---|---|---|---|---|
| ||||
|
Expand | ||||||
---|---|---|---|---|---|---|
| ||||||
|
Issues
Info |
---|
Issue is an item that is currently happening or has happened and is impacting the project. Issue Priority can be determined by assessing its potential consequences, such as delays, cost overruns, or impact on project scope. “Low” = Minor Impact “ Medium” - Medium Impact “High” -Major Impact “Highest” = Critical Impact Issues are also given a “Risk score”, based on Probability and Impact (see “Evaluating an Issue” below) Note:
For the action plan, you would use the Smart Checklist to document who is doing what to resolve the issue and when the action is due (for example, for an issue called "Many TSS risks are missing mitigation plans", I might have a Smart Checklist item called "Work with team to add mitigation plan to each risk - Tom Jones - 2/12/2025".
|
Expand | ||
---|---|---|
| ||
|
Expand | ||||||
---|---|---|---|---|---|---|
| ||||||
|
Decision
Info |
---|
The decision log tracks major decisions made throughout the project.
Note:
|
Expand | ||||||
---|---|---|---|---|---|---|
| ||||||
|