Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Version History

« Previous Version 5 Next »

\uD83D\uDC65 Participants

  1. Erin

  2. Judy

  3. Mindy

\uD83E\uDD45 Goals

  • Resource allocations

  • Roadmap

  • Backlog items

  • Risks/escalations

 

Time Tracking: AHM-789

\uD83D\uDDE3 Discussion topics

Roadmap

https://tableau.ucsd.edu/#/views/MindyMilestones/ProjectMilestoneGantt?:iid=2

Resource allocations and utilization

https://tableau.ucsd.edu/#/views/AllocationActuals/FYTD/0c31b3bc-0a06-4594-a4d5-4b3dee01a241/BIA?:iid=1

image-20240423-234954.png

image-20240423-235745.png

Projects

*Go live dates inaccurate where scope missing, or allocations need to be updated

AH plan: https://its-pro.ucsd.edu/secure/PortfolioReportView.jspa?r=AGfFr

Summary view: https://its-pro.ucsd.edu/secure/PortfolioEmbeddedReportView.jspa?r=akdyP&t

Project

Discussion Items

AIs

1

IRR

  • unclear scope for phase 2 and 3

  • program review - how many dashboards? Who from IR can Galina work with?

  • historically, BIA has gone after the data sources

    • investigate which ones are mapped to Program Review

  • highest priorities these next 2 weeks: CLSD and Census

  • Aymme has extracts that should cover majority of what IR needs

    • SAHR-2355 - Getting issue details... STATUS

    • this could be a template that IR can follow

    • Sama needs to conduct gap analysis after validation

  • RACI

    • expectations from IR

    • Validations

  • when BIA releases new field for IR, expectation is IR will test during the UAT period

    • Not just Galina, original requestor too

    • what are role expectations

    • present options (i.e. if only Galina test, then accept risk)

  • Mindy dig into program review docs and update OTL (add bug fix time, add reports for phase 3 into OTL)
  • Mindy rescope IRR for SLCM ; what add’l resources are needed if want all reports to be sourced from SAH
  • Mindy create doc - clear roles and responsibilities
2

Jira in RAH project

  • project charter

    • PR records already have the fields from charter

    • some groups still use charter doc with their business teams

    • in future, fill out PR record even if there’s unknowns

  • annual planning

    • what’s ADIS' bandwidth?

  • impact to existing projects

    • IR?

    • unknown what integrations are needed

    • cost analysis?

    • 1 time cost for new project vs recurring costs

    • OCGA set up connector from Tableau to Jira

      • keeps breaking

      • blocks upgrade to Tableau (compliance issue)

      • should reside in RAH

    • IRB would be delayed

  • pause enhancements for next 3 yrs?

    • lose funding for Andy

    • learning curve

  • challenge

    • lack of BI workers (FACE team)

    • lack of bsa

  • half of Sama is funded by external projects

  • Does Bill’s team have resource availability - Mindy
  • Mindy reply to OCGA on next steps (dependent on Concur, COI and C2 completing), IRB will be deprioritized
3

https://support.ucsd.edu/sn_customerservice_case.do?sysparm_tiny=1YCqZIIgZBUQCaOl9deV8fdkXWw9GfyI&sys_id=3d46e2f81b677c50b8d255b5604bcb50&sysparm_record_row=8

4

Legacy DW and SAH Sources

/wiki/spaces/SAHRS/pages/816644103

SAH

  • ISIS

  • Canvas

  • ApplyUC

  • ProSAM

  • VAC

  • Hops (db, not a source system)

  • Slate Grad

  • STLNK (db, not a source system)

  • STUDENT_DB (db, not a source system)

  • OGS (db, not a source system)

  • HDH

  • Kaltura

  • EVC-SQL-SERVER (db, not a source system)

  • Transact

  • Accounts Receivable

  • AEPNexus (in progress)

  • Oasismatrix (in progress)

Legacy DW

  • AR

  • ISIS

  • ProSAM

  • ApplyUC

  • Mindy follow-up with Jen Hernandez if Greg Boyer can help us with legacy list
5

PR-1055 - Getting issue details... STATUS

Kevin’s syncing with Invenio to create SOW

6

PR-1060 - Getting issue details... STATUS

  • tight timeline

  • coordinating deployment with Bars team (UCSD, Merced, UW, and ASU)

7

PR-983 - Getting issue details... STATUS

  • 4 Beta views is out in Cognos for testing

  • need Cindy/Silvia approval on data groupings so can progress with SNOW form

8

PR-987 - Getting issue details... STATUS

  • loading SIS tables

  • UW is devising authentication plan on their jumphost

  • config meeting w/Kenny scheduled to walk through config file, materialization process

9

PR-910 - Getting issue details... STATUS

  • get to green

  • CLSD is highest priority

  • Galina is validating Instructor assignment bug fix

  • Galina will push custom data source early next week so Olga can continue report rebuild

10

PR-384 - Getting issue details... STATUS

  • Project close after occuspace view is released to prod in June

11

PR-385 - Getting issue details... STATUS

  • waiting for Jennifer’s team to finish UAT (planning to finish in June)

  • project close end of June

12

PR-1084 - Getting issue details... STATUS

  • DDC meetings have started

  • meeting scheduled with Angela to discuss charter questions

13

backlog

PR-992 - Getting issue details... STATUS

PR-988 - Getting issue details... STATUS

PR-972 - Getting issue details... STATUS

PR-1053 - Getting issue details... STATUS

PR-1029 - Getting issue details... STATUS

PR-206 - Getting issue details... STATUS

PR-1003 - Getting issue details... STATUS

PR-1000 - Getting issue details... STATUS

PR-1001 - Getting issue details... STATUS

PR-1002 - Getting issue details... STATUS

14

Current AH project portfolio

key summary type priority status Project go live date Project Health Executive Project Update OTL Status
Loading...
Refresh

  • No labels