\uD83D\uDDE3 Discussion topics

Item

Notes

Red Projects (FYI)

  • FSPT

  • IRR

  • Canvas2

  • CourseLeaf (freshly red)

    • Red for Risks (which will likely turn into Red for Sched):

      • Integrations scope >> still undecided, will have schedule impact, likely 6-8 months

        • Mitigation: only queued up changes, vs retrospective data

          • escalate decision, move forward without perfect estimates

      • Solution architect resourcing >> oversliced, mitigation brainstorming planned for

VK mtg next week, proposed deck

usual, data in PPMO dash https://tableau.ucsd.edu/views/PPMODashboard/PPMODashboard

volatility:

  • Dev0.1 and Canvas2?

  • NGN?

  • Draw straws? (smile)

Metrics for top projects

  • ESR SIS (TSS+)​

    • Mainframe Deprecation​

  • Campus Activation (Events+)​

  • Secure Connect (Cybersecurity Enhancements)​

  • Triton GPT

  • Identity and Access Management

  • Anaplan

Major gates?

  • Planning complete, design complete, build complete, testing complete, go live complete

    • Risk: overly waterfall/linear

% slide?

  • Will only be able to calc based on baselined sched

Canvas2

data point to sticky areas?

v3 - how much are we missing dates

Major go lives

  •  NGN, MCN, HSIT July posting
  • Done, project planned to close after two more posts, service transition plan and roadmap completed

  •  SAH: Dev0.1 and Canvas2, 8/20-26

  • Key timeline

    • STALE TIME: starts 8/20

    • DOWN TIME: starts 8/21

    • Core views are back up and refreshed on 8/22

    • LMS views are back up and refreshed on 8/26

  • /wiki/spaces/SC2P/pages/1381695844

    • Back up will be taken of key tables of SAH, as roll back mitigation

  • /wiki/spaces/SC2P/pages/628295455

    • Issue: cutover and go / no go was not socialized through SISC; will ensure future Dev0 releases managed in partnership with overall ESR SIS, due to impact/risk to SIS and SAH prod

Projects closed

GWED

Capacity and Resource Allocations

proposed updates, based on last FY actuals

Lref gdrive file
urlhttps://docs.google.com/spreadsheets/d/1hH7Pg2AN2ruInZ4kqEvsDfCxMRZIaOvVWEFqkeXEuBk/edit?gid=1766582641#gid=1766582641

image-20240814-003351.pngImage Modified

outcomes:

80% blanket, for standard

  • Prof dev below the line, adds value, and is often part of a project

  • for managers, different model (more HR time)

  • continue to work to clean up how work is structured, so things that are incorrectly rolling up to admin

Projects closed

GWED

Facilities AH Core

✅ Action items

  •  

⤴ Decisions

...