\uD83D\uDDD3 Date

\uD83D\uDC65 Participants

\uD83E\uDD45 Goals

\uD83D\uDDE3 Discussion topics

Item

Notes

Red Projects (FYI)

  • FSPT

  • IRR

  • CourseLeaf

    • Red for Risks (which will likely turn into Red for Sched):

      • Integrations scope >> still undecided, will have schedule impact, likely 6-8 months

      • Solution architect resourcing >> oversliced, mitigation brainstorming planned for

VK mtg next week, proposed deck

Major go lives

  • NGN, MCN, HSIT July posting
  • Done, project planned to close after two more posts, service transition plan and roadmap completed

  • SAH: Dev0.1 and Canvas2, 8/20-26
  • Key timeline

    • STALE TIME: starts 8/20

    • DOWN TIME: starts 8/21

    • Core views are back up and refreshed on 8/22

    • LMS views are back up and refreshed on 8/26

  • /wiki/spaces/SC2P/pages/1381695844

    • Back up will be taken of key tables of SAH, as roll back mitigation

  • /wiki/spaces/SC2P/pages/628295455

    • Issue: cutover and go / no go was not socialized through SISC; will ensure future Dev0 releases managed in partnership with overall ESR SIS, due to impact/risk to SIS and SAH prod

Projects closed

GWED

Capacity and Resource Allocations

proposed updates, based on last FY actuals

image-20240814-003351.png

✅ Action items

  •  

⤴ Decisions