2024-08-14 Meeting notes

2024-08-14 Meeting notes

 Date

Aug 14, 2024

 Participants

  • @Erin Kilburn

  • @Amini, Mojgan (Deactivated)

  • @Kevin Chou

  • @Anna Nordeen

  • @Brett Pollak

  • @David Rapp

  • @Arlene Yetnikoff

 Goals

  •  

 Discussion topics

Item

Notes

Item

Notes

Red Projects (FYI)

  • FSPT

  • IRR

  • Canvas2

  • CourseLeaf (freshly red)

    • Red for Risks (which will likely turn into Red for Sched):

      • Integrations scope >> still undecided, will have schedule impact, likely 6-8 months

        • Mitigation: only queued up changes, vs retrospective data

          • escalate decision, move forward without perfect estimates

      • Solution architect resourcing >> oversliced, mitigation brainstorming planned for Aug 19, 2024

VK mtg next week, proposed deck

usual, data in PPMO dash https://tableau.ucsd.edu/views/PPMODashboard/PPMODashboard

volatility:

  • Dev0.1 and Canvas2?

  • NGN?

  • Draw straws?

Metrics for top projects

  • ESR SIS (TSS+)​

    • Mainframe Deprecation​

  • Campus Activation (Events+)​

  • Secure Connect (Cybersecurity Enhancements)​

  • Triton GPT

  • Identity and Access Management

  • Anaplan

 

Major gates?

  • Planning complete, design complete, build complete, testing complete, go live complete

    • Risk: overly waterfall/linear

% slide?

  • Will only be able to calc based on baselined sched

 

Canvas2

data point to sticky areas?

v3 - how much are we missing dates

Major go lives

NGN, MCN, HSIT July posting
  • Done, project planned to close after two more posts, service transition plan and roadmap completed

 

SAH: Dev0.1 and Canvas2, 8/20-26

 

Capacity and Resource Allocations

proposed updates, based on last FY actuals

 

image-20240814-003351.png

 

outcomes:

80% blanket, for standard

  • Prof dev below the line, adds value, and is often part of a project

  • for managers, different model (more HR time)

  • continue to work to clean up how work is structured, so things that are incorrectly rolling up to admin

 

Projects closed

GWED

Facilities AH Core

 

 Action items

 Decisions