Change Management
OCM Communications Schedule (ADKAR Phases: Awareness, Desire, Knowledge, Ability, Reinforcement)
Start with listing activities then go back and identify dates working back from Launch Date.
Check for gaps and then fill in as needed with input from the Core Team, ITS Teams, Finance Committees, and SMEs.
PHASE 2 OGL CHANGE MANAGEMENT PLAN
March 2024 --- June 2024
Week: | Date(s): | Status: | Projects: | Notes/Updates: |
---|---|---|---|---|
Week 1 | March 4-8, 2024 |
| Post Launch Review w/ OGL Team: Meeting w/OGL Team to review phase 1, post-launch, next steps (Wednesday, 11AM, via Zoom) Collect feedback from content developers and testers Send thank you’s + gift cards? @Ana Portlock Change Management Activities: Weekly office session on how to access and utilize the Oracle Guided Learning platform effectively. Update support channels (i.e., OGL Blink page) where users can seek assistance and share best practices. Communication Plan: Create tutorial videos or webinars demonstrating the features and functionalities of the platform, making it easier for users to navigate and engage with the content. Update OneDrive and Blink page with content. Overview: Kickoff meeting with stakeholders to introduce the Phase 2 Oracle Guided Learning Guide project. Conduct stakeholder analysis to identify key influencers and potential resistors. Begin drafting communication plan and training needs assessment. |
|
Week 2 | March 11-15, 2024 |
| [Reinforcement] Change Management Activities: Gather feedback from early adopters of the Oracle Guided Learning program to identify any challenges or areas for improvement. stakeholders can share their experiences and insights gained from participating in the launch + OGL, fostering a culture of collaboration and innovation. Address any technical issues or usability concerns raised by users promptly to ensure a smooth learning experience. Communication Plan: Overview: | OGL Phase 2 Launch Starting Point Assessment: https://forms.gle/APWUir6tkjwV1s959 |
Week 3 | March 18-22, 2024 |
| [Reinforcement] Change Management Activities: Communication Plan: Overview: |
|
Week 4 | March 25-29, 2024 |
| [Reinforcement] Change Management Activities: Communication Plan: Overview: |
|
Week 5 | March 29 - April 4, 2024 |
| [Reinforcement] Change Management Activities: Communication Plan: Overview: |
|
Week 6 | April 1-5, 2024 |
|
| |
Week 7 | April 8-12, 2024 |
|
| |
Week 8 | April 15-19, 2024 |
|
| |
Week 9 | April 22-26, 2024 April 29-May 3 |
|
| |
Week 10 | May 3 - June 30, 2024 |
|
|
PHASE 1 CHANGE MANAGEMENT
Week: | Date(s): | Status | Projects: | Notes/Updates: |
---|---|---|---|---|
Week 1 | Nov 20 - Nov 27 | done | Project Initiation and Planning: |
|
Week 2 | Nov 27 - Dec 1 | done | [Awareness] Needs Assessment and System Analysis Project Kick-off: Launch date/plan (develop schedule, courses/guides/sessions with subject matter experts) Stakeholder Analysis:. Project Planning: |
|
Week 3 | Dec 4 - 8 | done | [Awareness] (Solution Design) Current State Analysis: User Requirements Gathering: System Integration Assessment: |
|
Week 4 | Dec 11 - 15 | done | [Awareness] Development and Configuration System Design: Change Impact Assessment: Feedback and Approval: Documents: |
|
Week 5 | Dec 18 - 22 | done | [Awareness] (Refining) Implement Best Practices: User Training: Testing: |
|
Week 6 | Dec 24 - Tues Jan 2 | done | Holiday Closure: https://blink.ucsd.edu/HR/benefits/time-off/holidayclosures.html |
|
Week 7 + 8 | January 3 - 5 Jan 8 - 12 | done | [Awareness] (Review) Draft Launch Activities: |
|
Week 9 | Jan 16 - 19 | done | Monitoring and Optimization Performance Monitoring:
|
|
Week 10 | Jan 22-26 | done | Project Review and Next Steps User Feedback and Support: Optimization: |
|
Week 11 | Jan 29 - Feb 2 | done | [Knowledge] Testing (Content Creators--->OGL Testers) |
|
Week 12 | Feb 5- Feb 9 | done | [Knowledge] Testing (OGL Testers--->Final Reviewers) |
|
Week 13 | Feb 12 - 16 | done | [Knowledge] Testing (Final Reviews--->OGL Change Management Team) |
|
Week 14 | Feb 19 -23 | done | [Knowledge] System Go-Live (Post-launch): Change Management Activities: Communication Plan: |
|
Week 15 | Feb 26 - March 1 | done | [Ability] Project Review + Next Steps: Post-Implementation Review: |
|
Rollout Plan: Oracle Guided Learning System (OGLS) Communications
Phases | Dates | Plan |
---|---|---|
Phase 1: Content Development | (Deadline: Early January 2024) |
|
Phase 1 | February 2024 |
|
Phase 1 | March 2024 |
|