2023-04-07 PPMO Meeting notes

2023-04-07 PPMO Meeting notes

Date

Apr 7, 2023

Attendees

  • @Student Test - absent

  • @Vidal Espina

  • @Gerrity, Christopher (Deactivated)

  • @Erin Kilburn

  • @John Lane

  • @Angie Lu (Deactivated)  

  • @Lillian Maestas 

  • @Shawn Pappelbaum 

  • @Paul Krueger 

  • @Mindy Peng 

  • @Chris Ranglas 

  • @Brian Smith 

Discussion items

Time

Item

Who

Notes

Time

Item

Who

Notes



Share wins and cross functional project impacts and challenges

all

  • Wins

    • PP23

    • Work Location

    • MXOne Upgrade

  • X functional

    • Security - let’s talk about all the different projects and work happening here at our next mtg

  • Challenges





Health Statuses

 

PM Framework.pptx



Standardize health ratings based on data? Not possible with current data set/calculations, but want to determine better definitions so these are applied more consistently​

  • Schedule​

    • Missed milestone but recovery path to go live on time = yellow​

    • Missed milestone and at risk of missing go live = red​

      • Re baseline schedule and get buy in from stakeholders -> back to green​

      • Volatility? But if a new baseline, volatility will still remain high​ (separate measure than health)

      • Calculated end dates, target end dates for baselined schedule​

        • Charter: indicate if there is a hard go live date or compliance date (or range)​

  • Resourcing​

    • Yellow = not fully staffed for assigned tasks or resources oversliced/over allocated ​

    • Red = severe shortage and blocking project (makes schedule red)​

  • Budget​

    • Grey status / no status – no budget​

    • Yellow = approaching running out of budget but not out yet​

    • Red = over budget already or definitely will be over budget, or we have an open budget request​

  • Risk (Issues)​

    • Judgement?​

    • Open issue score of >6 or open risk score >9 = yellow​

    • Open issue impact of >8 = red 

 

When a project is undefined, but intentional/acceptable that undefined because still in initial planning: green (yellow is misleading)



What are you doing that's repeatable?



Think about this - great use case for Jira automation

  • repeatable OTLs for multiple plans (Lillian)

 

Repeatable tasks, for objects that weren’t in scope - prob ops/enhancements

Version updates, application version, upgrade











Standard Project OTL

@Shawn Pappelbaum 



 

Standard Events OTL

@Vidal Espina 

https://ucsdcollab.atlassian.net/wiki/x/lI72B











Request: schedule mtg w/ your SO to review projects and their portfolio







Reminder: project CoP 



Feb 21, 2023 



Related content