2023-10-13 PPMO Meeting notes

2023-10-13 PPMO Meeting notes

Date

Oct 13, 2023

Attendees

  • x@Student Test

  • @Vidal Espina- absent

  • x@Gerrity, Christopher (Deactivated)

  • @Karen Israel

  • x@Erin Kilburn

  • @John Lane - absent

  • x@Lillian Maestas 

  • x@Neti, Apoorva (Deactivated)

  • x@Shawn Pappelbaum 

  • x@Paul Krueger 

  • x@Mindy Peng 

  • @Chris Ranglas 

  • @Brian Smith 

Discussion items

Time

Item

Who

Notes

Time

Item

Who

Notes



Share wins and cross functional project impacts and challenges

all

  • X functional

    • AI priorities https://ucsdcollab.atlassian.net/wiki/spaces/AI/pages/434208905

    • Roadmap and resource plan updates

    • SIS

      • Selection imminent; resource planning and OTL in progress

      • SFP decision anticipated this morning

  • Wins

    • Fixed Assets expected to close this month

    • Google Workspace expecting SNOW form to be live in early Nov

    • FaaS MVP and phase 1 complete (python); further steps will move into enhancements

      • Function as a Service - automating functions

      • Accelerate development, so dev can just make a form request and environment is auto created; x team work with BaRS and DIS

    • EAH Ecotime in backlog

  • Challenges

    • HDH SO transition and HDH Maximo; support from RMP and Adv https://rmp.ucsd.edu/

      • Pros: Mike very supportive of charter and planning

    • Resource planning and over allocations

    • Resistance to getting project charters completed

      • Best practice, project doesnt start until charter is completed

      • Should PMs support the charter creation?

        • If we are very close to the work, and could do in an hour or less

        • Sometimes groups needing a charter don’t know how to complete the charter; facilitate a session to complete the charters

        • Risk: perception of ownership of the project is with PMO vs SO or business

          • Imperative we get the necessary sign off

        • Recommendation: if it’s too support a function team, facilitate or pre draft

        • Moving to a form, PR fields

          • Will need to screen shot or otherwise memorialize the charter at time of approval, since the PR will be a living doc

 

Automations of reminders

 

Demo from Chris

 

Standard Project Collab Space: System Implementation; Sys Implementation 101

@Erin Kilburn

https://ucsdcloud-my.sharepoint.com/:x:/r/personal/ekilburn_ucsd_edu/_layouts/15/Doc.aspx?sourcedoc=%7B6a7b7e2d-264b-4489-97d4-b3b01dbed37d%7D&action=editnew&wdPreviousSession=9d0e7929-1955-4837-afde-7253d396f750&wdNewAndOpenCt=1689715343481&wdo=4&wdOrigin=wacFileNew&wdTpl=blank&wdLcid=1033&wdPreviousCorrelation=2577fc30-9784-4d53-aba2-f8bf7be5047a

 

Campus Press @Karen Israel
Lock shop @Neti, Apoorva (Deactivated)
various AH projects @Mindy Peng , @Neti, Apoorva (Deactivated)

 

Portfolio clean up

 

Links to charters, collab spaces, ITS PRO

Next: Actual dates projects complete vs what was originally put in charter

 

Project coordinators

 

 

 

Closed / done project - when they were done vs said they were done

 

issue: made up dates, without supporting WBS and schedule upon project approval (need for additional gate)

issue: continually changing priorities

 

Closing projects! Should be Live

 